1. Preinstallation coordination
Confirm locations, equipment requirements, access, and division of responsibility before rough-in.
0/10
2. Video-board power
Four total video-board circuits: three new from LA3 and one relocated existing circuit.
0/10
3. AV-rack power
One new dedicated circuit, separate from the four video-board circuits.
0/6
4. Power pathways
Install complete raceway systems with supports, boxes, fittings, bushings, and pull access.
0/10
5. Low-voltage pathways
Make all new and repurposed data pathways ready for a complete video system.
0/10
6. Cat6 cable installation
Install six complete Cat6 CMP solid-copper links and preserve service slack.
0/10
7. Cat6 termination and rack work
Twelve total terminations: six rack-side and six remote jacks.
0/8
8. Penetrations and restoration
Leave the facility safe, sealed, clean, and visually consistent.
0/8
9. Testing and commissioning support
Verify electrical safety, cable performance, and end-to-end system readiness.
0/8
10. Closeout and acceptance
Turn over accurate records and obtain acceptance of the completed infrastructure.
0/8